camping pavilion extension

Three days and 9 tired workers later we can see the results of their labor. We added a 20x20 area the the camping pavilion that was constructed about 18 years ago under the direction of Mack Billeaud.
Ron Clausin and Nelson Jones came down from Bastrop First and ram-rodded a crew of 6 Teen Challenge guys that came to the camp to help out. This area will allow us to have much more room for our events and plenty of space to cook and prepare food without crowding out the area for dining and meeting.
We were able to finish all the framing and gable end facing and all the sheet metal roofing on one side. The rest of the roofing will be installed later this coming week.
Plans to modify the smoke stack on the cooker, place a grill top over the fire box, and install a tripple sink clean up area are also under way. We anticipate to have this completed in time to use at the upcoming Trace in January.





Thursday, December 10, 2009

camp pavillion extension



Construction has begun on the addition to the camping pavilion. We are adding 20 feet to the existing structure to have more room for the cooking area. We anticipate having it completed in time to use for the upcoming FCF Trace in January.